In a move that is aimed at promoting green sources of power, the central electricity regulatory commission (CERC) has reduced the threshold capacity for hydro and other renewable sources-based generating plants to qualify for grid connectivity.

While the minimum capacity required for thermal plants to seek grid access will be 250 mw, hydro and other renewable fuel-based power plants with 50 mw capacity will be eligible for grid connectivity. Plants with less than 50 mw individual capacity can also seek grid connectivity provided their aggregated capacity is 50 mw and they agree to undertake operational and commercial responsibilities through a mechanism of lead generator.

The CERC has taken the step after it came out that state transmission utilities were not in a position to provide grid connectivity to these power plants because of the high threshold capacity requirement.