Sivok-Rangpo Rail Project achieves major breakthrough
Sivok-Rangpo Rail Project achieves major breakthrough
Sep 18, 2023
Anish Mondal
This will boost rail connectivity to Sikkim
This will boost rail connectivity to Sikkim
Recently, it achieved physical progress of 57%
Recently, it achieved physical progress of 57%
Total length of rail line is 45 kms
Total length of rail line is 45 kms
It has 14 tunnels, 17 bridges & 5 stations
It has 14 tunnels, 17 bridges & 5 stations
Rail Line project falls under NFR zone
Rail Line project falls under NFR zone
83% of tunneling work completed
83% of tunneling work completed
Tunnel mining likely to be completed by Jan 31, 2024
Tunnel mining likely to be completed by Jan 31, 2024
Project was included in the Budget in 2008-09
Project was included in the Budget in 2008-09
Swipe up to know more
Swipe up to know more
Learn more