Everything you need to know about India’s 1st undersea tunnel in Maharashtra

The tunnel will be built using a tunnel boring machine and the New Austrian Tunneling Method (NATM), according to the tender document.

Everything you need to know about India’s 1st undersea tunnel in Maharashtra
The last date for bid submission is January 19, 2023. (Image: IE)

India’s financial capital Mumbai will be home to the country’s first undersea tunnel by next year. National High Speed Railway Corporation Limited (NHSRCL) invited this week bids for the construction of a 21-km-long tunnel, seven kilometre of which will be under the sea, for the Mumbai-Ahmedabad High Speed Rail Corridor.

According to the tender document, the tunnel will be built between the underground station at Bandra-Kurla Complex and Shilphata in Thane district of Maharashtra — thus connecting the two cities, reported PTI. The document further stated that the tunnel will be built using a tunnel boring machine and the New Austrian Tunneling Method (NATM).

Also Read | Centre approves Rs 10,000-crore re-development project to modernise three major railway stations – Check details

Here’s all that you need to know about India’s first undersea railway tunnel:

  • According to PTI, the seven-km undersea tunnel at Thane Creek will be the first undersea tunnel to come up in the country
  • The tunnel will be a single-tube tunnel to accommodate twin tracks. The section will include the construction of 39 equipment rooms at 37 locations adjoining the tunnel location
  • To construct this tunnel, tunnel boring machine (TBM) with a cutter head of 13.1 metre diameter will be used. Usually 5-6 metre diameter cutter heads are used for urban tunnels used in MRTS – Metro system, PTI reported
  • Three TBMs will be used to make about 16 km of the tunnel portion and the remaining 5 km will be through NATM
  • PTI further reported, this tunnel will be about 25 to 65-metre-deep from the ground level and the deepest construction point will be 114 metre below the Parsik hill near Shilphata
  • The last date for bid submission is January 19, 2023

Also Read | IRCTC got you covered with ‘Vrat Thali’ this Navratri – Check menu, prices, how to place order

The bids for the design and construction of underground Bandra Kurla Complex high speed rail station, including cut and cover length of 467m and ventilation shaft of 66 metre, was floated on July 22 and bids submission end date is October 22. In November last year, NHSRCL had invited bids for underground tunnelling works for the project. But it was cancelled this year with officials citing “administrative reasons”.