With the supply of coal being affected due to excessive rains, the government today said that contingency plan has been drawn up to overcome the hurdles in dispatch of supply to NTPC's thermal power plants, including Rihand and Vindhayachal.

The government has drawn up contingency plan for coal based power plants at Anpara, Rihand, Singrauli and Vindhyachal affected due to excessive rains in the Northern Coalfields Ltd (NCL) area during the last few days. (PTI)The government has drawn up contingency plan for coal based power plants at Anpara, Rihand, Singrauli and Vindhyachal affected due to excessive rains in the Northern Coalfields Ltd (NCL) area during the last few days. (PTI)

With the supply of coal being affected due to excessive rains, the government today said that contingency plan has been drawn up to overcome the hurdles in dispatch of supply to NTPC’s thermal power plants, including Rihand and Vindhayachal.

The government has drawn up contingency plan for coal based power plants at Anpara, Rihand, Singrauli and Vindhyachal affected due to excessive rains in the Northern Coalfields Ltd (NCL) area during the last few days, an official statement said.

“This unforeseen natural calamity has damaged roads, railway tracks and there is waterlogging in the open cast NCL mines. This has affected coal supply to Anpara, Singrauli, Rihand and Vindhyachal thermal power stations,” it said.

Contingency plan has already been implemented to ensure that the power supply due to this is not affected. If required, states can get the supply from alternate sources and power exchanges, it added.

The Sub Group Monitoring Committee reviewed the coal supply situation which was affected due to excessive rains and has issued a contingency plan to overcome the hurdles in coal supply to the thermal power plants receiving coal from Northern Coalfields Ltd (NCL).

“It has directed to the concerned agencies to put 6 numbers of Bogie Open Bottom Rapid discharge (BOBR) rakes in circuit for coal supply to Anpara and Singrauli thermal power station (TPS) till the merry-go-round (MGR) supplies to these plants are resumed,” it said.

“In addition to it, 2 Box ‘N’ railway rakes per day each from BCCL, CCL and ECL subsidiaries of CIL are being sent to the Rihand and Vindhayachal units of NTPC as the coal for these units is diverted to the Anpara and Singrauli TPS,” it added.

The imported coal stock lying at the port is also being moved to the Vindhayachal NTPC units. These pithead plants are designed to receive coal through MGR and therefore were facing difficulty in unloading coal through railway rakes. The coal supply is expected to improve in the next few days with the weather conditions improving.

The Sub Group Monitoring Committee consists of representatives of ministry of power, railways and coal besides Niti Aayog, CIL, and SCCL and is headed by Joint Secretary Ministry of Coal and reviews the coal supply situation to the power plants on a regular basis.

Despite incessant rainfall during past few days in some parts of the country, partially affecting coal mining operations and railway logistics, there is sufficient power available for grid requirement as reflected through grid stability maintaining a healthy daily average frequency in the range of 49.96-50.02 Hz, NTPC said in a statement.

Efforts are on to improve coal supply through a contingency plan drawn by CIL, the statement said.

Get live Stock Prices from BSE and NSE and latest NAV, portfolio of Mutual Funds, calculate your tax by Income Tax Calculator, know market’s Top Gainers, Top Losers & Best Equity Funds. Like us on Facebook and follow us on Twitter.

Next Stories
1Amazon, Flipkart, Snapdeal festive mega sale from Oct 1; here’s how to be smart with your spending
2Cipla gets four USFDA observations for three Goa facilities
3Online shopping may clock sales worth up to Rs. 25k crore: Assocham