39 mining projects of Coal India face delays

By: |
September 05, 2021 12:54 PM

Based on the demand projection in 'Vision 2024' for the coal sector in the country and subsequent demand projection on CIL, a road map has been prepared to project production plan in medium term.

Coal India accounts for over 80 per cent of domestic coal output.

State-owned CIL’s 39 coal mining projects are running behind the schedule on account of delays in getting green clearances and issues related to rehabilitation and resettlement (R&R).

This assumes significance in the wake of the country’s power plants grappling with depleting stocks at their end.

“114 coal projects with a sanctioned capacity of 836.48 mty (million tonnes per year) and a sanctioned capital of Rs 1,19,580.62 crore are in different stages of implementation out of which 75 projects are on schedule and 39 projects are delayed,” Coal India Ltd (CIL) said in its report.

The major reasons for delays in implementation of these projects are delay in forest clearances and possession of land and issues related to R&R.

CIL’s nine coal projects, with a sanctioned capacity of 27.60 million tonnes per year and a sanctioned capital of Rs 1,976.59 crores were completed with a total completion capital of Rs 1,958.89 crore during 2020-21.

Four of these projects belong to Western Coalfields Ltd (WCL), three of Central Coalfields Ltd (CCL) and two of Mahanadi Coalfields Ltd (MCL).

WCL,CCL and MCL are subsidiaries of Coal India.

One project with a sanctioned capacity of 1.4 million tonnes per year and a sanctioned capital of Rs 143.63 crore had started coal production during the year 2020-21, the report said.

CIL arm South Eastern Coalfields Ltd (SECL) is the mining project that started production during FY21, it said.

Coal India accounts for over 80 per cent of domestic coal output.

Based on the demand projection in ‘Vision 2024’ for the coal sector in the country and subsequent demand projection on CIL, a road map has been prepared to project production plan in medium term. Under this, CIL has envisaged one billion tonne coal production in the year 2023-24 to meet the coal demand of the country.

To achieve this target, CIL has identified major projects and assessed their related issues.

Get live Stock Prices from BSE, NSE, US Market and latest NAV, portfolio of Mutual Funds, Check out latest IPO News, Best Performing IPOs, calculate your tax by Income Tax Calculator, know market’s Top Gainers, Top Losers & Best Equity Funds. Like us on Facebook and follow us on Twitter.

Financial Express is now on Telegram. Click here to join our channel and stay updated with the latest Biz news and updates.

Next Stories
1MP govt has begun process to set up diamond park in Panna: Chouhan
2Scooter review: Hero Electric Optima HX very practical, but not yet aspirational
3RBI allows banks to sell fraud loans to asset reconstruction companies