Blueprint is ready for the Phase-II of World Bank-backed Kerala road KSTP (Kerala State Transport Project), even as the mele over the three-year delay in the Phase I of the $336-million project is piping down. Amidst the prolonged blame game, a senior executive of Malaysian contractor firm PATI had even committed suicide.
Designs are in place and the necessary land acquistion process is on, Kerala works minister Mons Joseph told FE. About 51 hectares of land have been acquired so far for the remaining 127 km of KSTP project.
During the Phase I that spilled over by three years, the Malaysian contractor PATI had not kept the deadline. State government, in its turn, had failed to make unencumbered land available for the project at the right time. This Phase of the 256-km road project is expected to be complete by December 2008.
Forgetting the unpleasant exchanges and the suicide of a key official over the project, PATI is back on Kerala terrain to work on KSTP. As earlier, it is partnered by Indian contractor Bhageeratha Engineering Ltd in the consortium PATI-BEL.
The good will comes with a price for Kerala government. The revised estimate for the final leg (upgrading 127 km) is for Rs 215 crore.
Quoting arbitration costs for the delay, Malaysian firm had claimed Rs 35 crore. In the last leg, the firm also gets 72.5% hike in rate.
Kerala government, however, says that the artbitration rates were negotiated down from the Rs 96 crore claimed. PATI had also originally asked for 80% hike in rate.
Out of the $336 million outlay for KSTP project, World Bank financing is for $255 million and State government’s share is $79 million.
Besides Malaysian PATI, Delhi-based Oriental Structural Engineers Pvt Ltd, Kerala-based Bhageeratha and another Malaysian firm Road Builder were involved in contract. Only PATI-led consortium’s share of the work was pending.