DPC
misdeclared availability: MSEB
Sanjay
Jog
Mumbai,
June 3: The Dabhol Power Company (DPC) had defaulted and misdeclared
the availability of power immediately after the commissioning of
Dabhol phase-I in May and July 1999, according to sources from the
Maharashtra State Electricity Board (MSEB) .
The board had
also planned to serve a total rebate of Rs 300 crore for these defaults.
However, it ultimately pardoned the DPC and verbally waived the
rebate.
MSEB sources
confirmed these misdeclarations and defaults, which took place before
January 28, February 13 and March 29, 2001. These sources told The
Financial Express that in view of the series of meetings between
the MSEB and DPC officials and clarification provided by the latter,
the rebate was not charged. “Had MSEB slapped rebate of around Rs
150 crore for May default misdeclaration, DPC was obliged to compute
it in its billing statement thereafter as MSEB is entitled to claim
rebate only at the end of four months block of January, May and
September,” sources added.
MSEB had argued
that as per the power availability curve incorporated by the DPC
in the power purchase agreement (PPA), it was entitled to provide
the instructed power by MSEB within three hours. However, during
these occasions, the DPC, though admitted that it had defaulted
on the availability of power, later clarified that the Dabhol plant
machines were new.
The DPC had
also questioned the board’s move to slap rebate in the past and
is believed to have told that MSEB cannot do so as the Dabhol plant
was developed on base load capacity and not peak load capacity.
MSEB had argued
that in terms of Clause 8.4(b) in the event of shortfall in delivery
of energy contrary to DPC’s declaration, Available Baseload Capacity
is calculated at ten times the difference between the Declared Baseload
Capacity (DBC) and the Active Power produced subtracted from the
total active power generation during that availability period or
hour.“This leads to a rebate (under Clause 10), which is meant to
adjust capacity payments made during the period having regard to
the Rated Baseload Capacity as well as to discourage misdeclaration
by DPC of DBC,” sources said.
Under Clause
10.2(b), the capacity payments payable by MSEB are subject to adjustments
of rebate in January for the first four months of the peak season
(October to January) and as per Clause 10.2(c) in May for the whole
of the peak season.
The board is
entitled to a rebate under these provisions. The DPC is obliged
under Clause 11.1(b) to compute such rebate in its billing statement
for the months of January, May and September. The reason being that
in the PPA the year is divided into the peak season (October to
May) and monsoon season (June to September).
In addition
to this, MSEB had said that the DPC should follow standard and not
ambient conditions at the time of declaration of base capacity.
|