Railways likely to defer freight corridor by 2 yrs
Anticipating problems related to land acquisition in West Bengal, the Railways might take a preemptive step of pushing by a couple of years the deadline for completion of its ambitious 3,300-km-long dedicated freight corridor project. Running through the eastern and western flanks of the country, the corridor will now be completed by 2018 instead of its earlier schedule of 2016, officials close to the matter told FE.
This is because the Railways still has to acquire around 1,000 acres of land in Bengal to lay the tracks for a section of the dedicated corridor and is apprehensive about completing this land acquisition on time, given the history of agitations for land in Bengal. And with the state being ruled by firebrand TMC leader Mamata Banerjee, an estranged ally of the Congress, there is fear that the acquisition process would not be smooth.
This is for the first time that Railways has taken into account the prevailing political situation to make adjustments in its project schedule.
The corridor, funded by Japanese banks and the World Bank, and to be built at an estimated cost of R90,000 crore, involves construction of 540 km of railway lines for freight movement spanning from Sonnagar in Bihar to Dankuni in West Bengal.
“We are in the process of notifying land in Bengal and once it is done, objections from land owners would be considered by the Railways and the local authorities. Given the history of land acquisitions problems in Bengal,