How the 5 states handled power

Comments 0
key constituent of the bijli, sadak, paani troika and which is often used as a yardstick for how governments have delivered on basic infrastructure.IE key constituent of the bijli, sadak, paani troika and which is often used as a yardstick for how governments have delivered on basic infrastructure.IE
SummaryThe smaller states generally seem to have done better on key measurable parameters.

has said absorbing the STL may excessively burden the budget and sought a change in the structure of the scheme.

Delhi

Delhi has made significant progress in ramping up capacity in sync with rising demand, despite constraints of land and fuel. Last fiscal, Delhi met a peak of 5,642 MW, up from 4,408 MW in 2009-10, and is gearing up to meet a peak of 6,000 MW this fiscal. The stateís own generation capacity increased from 982 MW to 2,200 MW during the 11th plan and another 2,800 MW is proposed to be added during the 12th, taking the total capacity to around 5,000 MW.

On the distribution side, Delhiís aggregate losses are down from 25.18 per cent four years ago to 15.15 per cent in 2011-12, as compared to the national average of 26.15 per cent. But the financial positions of the three private distribution utilities, especially the two run by BSES, are reported to be in bad shape.

Among showcase projects, the first 750-MW phase of the Bawana plant was commissioned in 2010-11. While the second 750-MW phase is almost ready for commissioning, the lack of supply of enough gas is holding up progress. Also, the project for islanding Delhi, which would put it on par with Mumbai, is being implemented and expected to be completed by 2013-end or 2014.

Madhya Pradesh

Generation capacity is up from 6,418.8 MW in March 2006 to 10,698.6 in March 2013. This is largely on account of capacity set up by central sector utilities, which have almost doubled capacity from 1,715.85 MW to 3,526.1 MW during the period. Also, while AT&C losses have come down from 37.79 per cent to 27.11 per cent between 2009 and 2012, these are still higher than the national average. The government says revenues have increased from Rs 4,521 crore in 2003 to 15,284 crore in 2013.

The governmentís promises include 24◊7 supply to non-agricultural consumers, 10 hours quality power for agriculture, and to make the state energy-surplus by 2014 with a focused thrust on solar, wind, small hydro and biomass projects. The contribution of renewable energy sources is targeted to go up from 5.31 per cent (499 MW) to 17 per cent (3,200 MW) by June 2015.

Mizoram

The small northeastern state managed to increase its installed capacity during the 11th plan by 15.6 MW and build 168.49 km additional transmission lines. Transmission and distribution losses at the beginning of the 11th plan were

Single Page Format
Ads by Google

More from Front Page

Reader´s Comments
| Post a Comment
Please Wait while comments are loading...