GAIL outlines $7.8-bn fleet-hire strategy to import LNG from US

Apr 28 2014, 01:25 IST
Comments 0
The PSU will soon float tenders to award contracts by November. The PSU will soon float tenders to award contracts by November.
SummaryTies up 5.8 mtpa starting 2017.

require six to seven years to deliver the first LNG ship, which does not meet GAIL's requirement. Generally, it takes 30 months for Japanese and Korean companies to deliver an LNG ship.

Building an LNG ship in an Indian shipyard would involve technical risks in terms of design and integration of the ship system. Moreover, Indian-built ships may be rejected by US terminals, according to consulting firm Integration.

In December 2011, GAIL signed a deal with Cheniere Energy Partners to buy 3.5 mtpa of LNG from the Sabine Pass Terminal in Louisiana on FoB basis. Deliveries would start between March and August 2018. In April 2013, GAIL booked another 2.3 mtpa capacity to export LNG from the Dominion Cover Point terminal in Maryland, delivery of which is expected from September 2017.