Vedanta’s Orissa project in troubled waters

Dilip Bisoi
Posted: Monday, May 05, 2008 at 2308 hrs IST
Updated: Monday, May 05, 2008 at 2308 hrs IST


Font Size

Print

Feedback

Email

Discuss
  • Discount Shopping

Bhubaneswar: London-based Vedanta Resources’s chairman Anil Agarwal may be claiming that his projects in Orissa are well on schedule, but the ground reality is somewhat different.

The group’s Rs 8,400 crore aluminium project in Orissa is in serious trouble. With locals snapping the water supplyline to the project, work on the site at Jharsuguda has been affected.

After the farmers denied water from the Hirakud reservoir for the project, Vedanta was relying on water from a small rivulet, Veden, for its project works. However, the locals have stopped that supply source, too. The villagers have been complaining that they were not getting water as Vedanta was sucking up a huge quantity from the rivulet.

Vedanta Aluminium Ltd, a Vedanta Resources company, is setting up a 5 lakh tonne aluminium smelter with an investment of Rs 8,400 crore at Jharsuguda. In the first phase, the company has set up a 2.5 million tonne smelter and a captive power plant (CPP) of 1,215 mw (9X135mw).

Due to the water problem, commissioning of the aluminium smelter and the CPP is likely to be delayed.

The first phase of the aluminium smelter and the CPP is almost complete and ready for commissioning. However, with no water from the Hirakud reservoir, the commissioning could not take place as scheduled.

A couple of months back, the company vice-president (commercial & project), AK Samal had told the media that production from the first phase of 2.5 lakh tonne facilities would commence by March 2008. He had also said that the first phase of the 675mw (5X135mw) CPP of the smelter was expected to go for generation in the new year.

‘’The commissioning is likely to be delayed by about a year’’, said a senior officer involved in the project. According to him, the issue of water from the Hirakud reservoir was not likely to be resolved before the general elections early next year.

The ruling Biju Janata Dal-Bharatiya Janata Party government was unlikely to take a decision that would hurt the sentiments of farmers in the penultimate year to the elections, he added.

Farmers living in the command area of Hirakud reservoir have been agitating against sharing the water with industries. They have destroyed the infrastructure built by industries to source water from the reservoir.

Recently, Agarwal said at Bhubaneswar that the company was ready to invest Rs 30 crore to make temporary measures to source water from the downstream of...

More from

Single Page Format 1 - 2 - Next
Discuss this story on expressindia forums

Post Comments

Comments: (Limit 3,000 characters)
Name
Message
Email ID
Subject
TERMS OF USE:
The views, opinions and comments posted are your, and are not endorsed by this website. You shall be solely responsible for the comment posted here. The website reserves the right to delete, reject, or otherwise remove any views, opinions and comments posted or part thereof. You shall ensure that the comment is not inflammatory, abusive, derogatory, defamatory &/or obscene, or contain pornographic matter and/or does not constitute hate mail, or violate privacy of any person (s) or breach confidentiality or otherwise is illegal, immoral or contrary to public policy. Nor should it contain anything infringing copyright &/or intellectual property rights of any person(s).
I agree to the terms of use.

Comments
» Supply of Cast Steel Yoke
Posted by Binayak Technology, on 2008-10-15 12:43:58.723877+05:30
We are specialised manufacture

Express Classifieds
Post and view free classifieds ad
Express Astrology
Know what's in the stars for you