Rural roads head nowhere

Oineetom Ojah
Posted online: Tuesday , June 17, 2008 at 23:30 hrs
Updated On: Tuesday , June 17, 2008 at 23:30 hrs


Font Size

Print

Feedback

Email

Discuss
Rate This Article
1 2 3 4 5 6 7 8 9 10
Rating:  0

Soaring steel and cement prices have virtually put the brakes on the Pradhan Mantri Gram Sadak Yojana (PMGSY), the rural road component of the UPA’s flagship ‘Bharat Nirman’ programme. While rising input costs are affecting other road projects as well, rural road projects are worst-hit as contracts awarded under the PMGSY are fixed-price contracts with no room for price variations.

Responding to the fact that not many contractors have responded to new tenders and several contractors have preferred to exit ongoing projects mid-way fearing significant losses as the government would not permit any price escalation, the RD ministry is considering taking a relook at the pricing provisions.

Between January 2006 and May 2008, prices of cement went up 1.48 times, steel prices soared 1.56 times and bitumen rates rose by a whopping 1.94 times. During a review of Bharat Nirman projects last week, the rural development ministry has admitted that under the present circumstances it will not be able to complete the programme by 2009.

The ministry is working on a Cabinet note to allow changes in the approved cost of projects mid way to help finish the rural road scheme ahead of the general elections. To find a way out of the current quandary, the ministry has also set up a committee under principal secretary,public works department, Rajasthan, CS Rajan along with principal secretaries of departments handling the scheme in Assam, Maharashtra, Himachal Pradesh, Madhya Pradesh and Orissa. It is expected to submit its report next month.

More trouble Implementation of the programme has also been affected by a shortage of stone aggregates in some areas of Bihar, Assam , Tripura, West Bengal and Orissa. The states have been asked to augment supplies through better utilisation of existing sources and tapping new sources.

The government is also considering streamlining and simplifying the procedures for permits to ensure timely and adequate availability of inputs. It would further rationalise the high royalty charges for construction material charged by Assam , Maharashtra , Chhattisgarh, Haryana and Orissa.

The ministry has asked states with a high backlog of new connectivity projects to deploy enough dedicated programme implementation units (PIUs). The key states behind on this front are Assam (with 41% target achieved), Jharkhand (10% achieved), Uttaranchal (10% achieved), Bihar (14%) and West Bengal (22%).

Another critical factor affecting the scheme is non-availability of land. The ministry has suggested that the states...

Single Page Format 1 - 2 - 3 - Next
Ads by Google

Post Comments

Comments: (Limit 3,000 characters)
Name
Message
Email ID
Subject
TERMS OF USE:
The views represented here are not neccesarily endorsed by www.financialexpress.com and its allied websites. All messages will be moderated and no message that has inflammatory, abusive, derogatory language or any language deemed unfit for publication by the editor will be displayed. Though it will be endeavoured that as many messages as possible be displayed, there will be time lag between the submission and publication of the messages. The website reserves the right to publish or reject any message.
I agree to the terms of use.

Comments
Shaadi Matrimonials
Get Marriage Proposals by Email EVERYDAY!
Register FREE on Naukri.com.
200000+ Hot Job Openings!
Yatra Offers
10% cash back on Master Card
Send Gifts
Flowers and Gifts
Express Classifieds
Post and view free classifieds ad
Express Astrology
Know what's in the stars for you