NTPC’s move to light up Games will trigger loadshedding in rest of India

Comments print
Indronil Roychowdhury: Kolkata, Sep 18 2010, 00:57 IST
Come October 3 and the country is likely to plunge into darkness as NTPC diverts the states’ share of power to New Delhi for the CommonWealth Games (CWG). Delhi will require 5,000 mw for the Games. Damodar Valley Corporation (DVC), Indira Gandhi Super Thermal Power Project, Pragati Power Corporation and NTPC’s Dadri Thermal Power Station were to meet the requirement, however, except NTPC’s Dadri unit (2x490mw), none of the project have come up to power the Games.

While only a 490-mw unit of NTPC’s newly commissioned Dadri unit was supposed to supply power for the Games, the entire 980 mw generated will have to be diverted to Delhi during the CWG, said an NTPC official. According to the formula agreed upon, Uttar Pradesh was to get 5% of the 980 mw generated and 50% would have been distributed across the country. Delhi was to get 45% of Dadri’s generation. Even after drawing the entire generation of Dadri project CWG would fall short of 4,020 mw, to be managed from the states’ share of NTPC generation. This would violate the Gadgil power sharing formula, overdrawing from the grid, also virtually breaking grid discipline.

According to a Power Grid Corporation official, there are already instructions that the uniformity of frequency for supplying the common pool power to the north, east, west and north east India has to be broken during the CWG and power to north should flow at a higher frequency. In fact the eastern, western, northern and north eastern power

... contd.

Ads by Google
   1 | 2 | Next
Previous Story  Quick View Next Story  Defence ministry goes slow on downlisting firms for aircraft deal
Reader's Comments| Post a Comment

Be the first to comment.

Post your Comment

Your email address will not be published. Required fields are marked *

Name *
Email *
Message *
 
captcha
please enter the above characters in the box below