10 floors in 48 hours: Mohali skyscraper starts taking shape

Comments print
Express news service :Mohali, Nov 30 2012, 01:50 IST
B.jpg
project, said the construction technology, first-of- its-kind in India, was unique in many ways. All the components of the building were manufactured in the factory, pre-fitted with floors, water supply, wiring, sanitation, air conditioning ducts and everything else. These were then shifted in the state-of-the-art transporting vehicles to the actual site for installation.

More than 80 per cent of the work is done in the factory. Concrete is used only in foundations and 3-inch deck floorings in this nut-and-bolt structure, thereby minimising the usage of concrete. No scarce resources like bricks, sand or gravel is used. Since it is an ultra fast technology of construction with less than 20 per cent of work at site, there is minimal emission of flying dust and less pollution of water at site. The external façade of the building is double-skinned PUF panel that ensures thermal insulation.

“This construction mechanism has been approved by the Council of Scientific and Industrial Research-Structural Engineering Research Centre (CSIR-SERC), Chennai. The model has also been cleared for the zone V seismic area which is the highest,” Harpal added.

Ads by Google
   Previous | 1 | 2
Previous Story  Rs 3,932 cr supplementary budget presented in Odisha assembly Next Story  No irregularity in sale of land to Wave Infrastructure, says Akhilesh Yadav
Reader's Comments (1)| Post a Comment

Construction time

N K Roy | 04-Jan-2013Reply | Forward
Overall construction time include beginning of the fabrication not the erection period only. So, my question is "how long is the fabrication period?".