|
NTPC
unable to fund capacity addition under ABT tariff ordered
by CERC
Sanjay Jog
Mumbai,
Aug 28: STATE-RUN
National Thermal Power Corporation (NTPC) would not be in
a position to finance the capacity addition of 21,180-MW from
the existing 19,935-MW till 2011-12, under the availability
based tariff (ABT) ordered by the Central Electricity Regulatory
Commission (CERC).
The company had projected the fund requirement of Rs 1,06,352
crore, comprising Rs 31,733 crore internal debt, Rs 42,311
crore foreign currency debt and internal resources of Rs 32,308
crore.
According to AF Ferguson & Co, which reviewed NTPC’s financial
projections in the wake of implementation of ABT, internal
resources available were estimated to be Rs 14,209 crore,
as against the requirement of Rs 32,308 crore. However, there
would be a shortfall of Rs 18,000 crore in the internal resources
(IR) vis-a-vis the IR required. “Under the ABT regime, the
IR available cannot support the capacity addition of 21,180-MW
by the year 2012,” the AF Ferguson & Co report said.
Under the ABT regime, NTPC would be in a position to undertake
capacity addition of new projects in the range of only 6,250-MW
as against 15,980-MW as planned earlier under the two-part
tariff structure. The list of the projects worked out for
the new capacity addition of 6,250-MW included Rihand II -1,000-MW,
Ramagundam III -500-MW, Kodam 800-MW, Sipat-I -1980-MW, Kawas-II
-650-MW, Kahalgaon II -1,320-MW. In addition to this, considering
the internal resource availability, North Karanpura (1,980-MW)
can be commenced in 2009-10, but completion would be in XII
plan. The total funds required for the capacity addition of
6,250-MW would be Rs 58,085 crore, comprising local borrowings
of Rs 17,253 crore, foreign currency debt of Rs 23,004 crore
and internal resources worth Rs 17,828 crore. The IR available
would be adequate to meet the IR requirement to fund the capacity
addition of 6,250-MW.
According to AF Ferguson & Co, the IR available would
not be adequate if the generation level falls by even 1 per
cent against the base assumption. NTPC had assumed plant availability
factor and plant load factor at the threshold level (80 per
cent and 77 per cent respectively) to recover 100 per cent
of the annual fixed charges.
The report said that a major concern of NTPC was the level
of sales collection which would have a major impact on the
IR available to finance the expansion plan. One of the key
assumptions for sales collection related to the extent of
realisation of current billing in the same year and the balance
in the subsequent years, subject to a debtors level of 5.5
months or more. Based on this assumption, the debtors outstanding
as on March 31, 2012 worked out to 5.5 months of sales.
|